Success Story•Scappoose, OR

Commercial Building Pad Site Prep in Scappoose, Oregon

By Curtis Miller, Owner · Excavation, land services & gravel delivery in Northwest Oregon

Aerial view of a finished 3/4 inch minus commercial building pad and driveway on a cleared lot in Scappoose, Oregon

Quick summary

On a lot in Scappoose, Oregon, that we had cleared of white oak trees a few months earlier, we built a complete pad for a commercial-style building. We removed 3 to 4 feet of topsoil to reach a hard round-rock subbase, then built the pad up in compacted lifts of 3/4" minus, more than 4 feet deep in places, with geotextile fabric under the driveway and future asphalt. More than 200 truckloads of rock were placed, the work was completed in under a week, and every compaction test passed.

Location
Scappoose, OR (Columbia County)
Project Price Range
$50,000+

The Project

This client was constructing a commercial-style building on this lot. A few months earlier, we had cleared the lot of white oak trees and hauled off the vegetation, stumps and debris.

The next phase was a complete building pad, ready for construction.

Before and after aerial views of an oak-covered lot turned into a finished commercial building pad in Scappoose, Oregon
Before and after: from oak forest to a finished building pad.

Digging Down to a Solid Subbase

Because the building area had previously been forest, the topsoil was extremely deep. We removed 3 to 4 feet of topsoil and vegetation to reach a solid subbase.

All of the excavated material remained on site and was graded out across the rest of the property.

The subbase turned out to be hard round rock, so heavy-duty base rock was not required.

Building Up in Lifts

The project required compaction testing, and we used 3/4" minus for the entire build. The pad was built up in lifts, with each layer compacted before the next was placed. Some areas of the pad contain more than 4 feet of 3/4" minus.

Dump truck delivering 3/4 inch minus next to geotextile fabric on a commercial site prep job in Scappoose, Oregon
Rock deliveries coming in, with geotextile fabric rolled out.
Dump truck, roller and track loader working on a commercial building pad site in Scappoose, Oregon
Trucks, a roller and a track loader working the site.
Track loader and roller on a compacted 3/4 inch minus building pad in Scappoose, Oregon
Spreading and compacting each lift of 3/4" minus.

Geotextile Fabric Under the Driveway

We installed geotextile fabric under the driveway and the areas to be paved with asphalt later, keeping the rock separated from the soil below.

New 3/4 inch minus driveway curving into a commercial building pad site in Scappoose, Oregon
The driveway into the site, built over geotextile fabric.

More Than 200 Truckloads in Under a Week

More than 200 truckloads of rock were delivered, and the entire project was completed in under a week.

Graded 3/4 inch minus building pad with excavators and a track loader in Scappoose, Oregon
The pad graded to finish.
Finished, compacted 3/4 inch minus building pad with grade stakes in Scappoose, Oregon
The finished, compacted pad.

The Result

Every compaction test passed, the owner was very pleased, and the site is now ready for construction.

Finished commercial building pad ready for construction in Scappoose, Oregon
The finished building pad, ready for construction.

Materials Used

3/4" minus for the entire pad, placed and compacted in lifts (over 4 feet deep in places) on a natural round-rock subbase, with geotextile fabric under the driveway and future asphalt areas.

What a Project Like This Costs

Typical range

$50,000+

Commercial building pads like this one, with deep excavation, hundreds of loads of rock and compaction testing, usually run $50,000 or more.

What affects the cost

Every property is different, so the cost of similar projects can vary. The main factors are:

  • Depth to a solid subbase. The deeper the topsoil, the more excavation and the more rock it takes to build back up.
  • Amount of rock. Large pads and deep fills can take hundreds of truckloads.
  • Haul distance. The distance between the quarry supplying the material and the job site.
  • Material pricing. Rock prices vary by quarry and by material type.
  • Compaction requirements. Commercial pads that must pass testing take careful lift-by-lift placement.
  • Fabric and driveways. Geotextile fabric and access driveways add material and time.

Planning a similar project? We're happy to talk through what you have in mind and give you a free estimate.

Common Questions

How deep do you have to dig for a building pad?

Deep enough to get below the topsoil and organic material to a firm subbase. On this lot, which had been forest, the topsoil ran 3 to 4 feet deep, so that's how far we excavated before building the pad.

Why build a pad in lifts?

Placing rock in layers and compacting each one before adding the next is the only way to get the whole depth uniformly dense. That's what lets a pad pass compaction testing and carry a building without settling.

When is geotextile fabric used on a commercial site?

Fabric goes under driveways and areas that will be paved, where it separates the rock from the soil below and helps the base stay stable under traffic.

Planning Something Similar?

See how this lot was cleared of oak trees, or see our site preparation, Scappoose site preparation and gravel pads, or request an estimate and we'll take a look at your property.

← All success stories

Have a similar project?

Planning a Project in Scappoose?

Whether it's a parking lot, a building pad or a driveway, we'll walk your site and give you a clear estimate. Request an estimate, or call or text us today.

★ 5.0 Google Rating  ·  Licensed, Bonded & Insured  ·  Local & Family-Run

Graded backyard beside a new home and fence in Hillsboro, Oregon

★★★★★

5.0 on Google

Call Us Request Estimate